Company:China Mineral Processing & Metallurgy League
Email: Bonnie@hotminingepc.com
Phone:+86 18252116933
Fax:+86 10 58646590
Address:Room10811, Floor8, Building A, Galaxy SOHO, Dongcheng Dist, Beijing, P.R.China
Application of Raise Boring Machine/Raise Drill/Drilling Machine
Application Background
A mine in Pakistan encountered difficulties about community environmental constraints during the development of the vertical shaft.
Vertical shaft parameters: diameter=2m, depth=100m, the shaft has been drilled through the underground to be used as a wind inlet.
Shaft stratum: tight sandstone, limestone, etc. The maximum uniaxial compressive strength of the rock is about 80 MPa.
Environmental restrictions: Due to the
environmental constraints of the ground community, it is not allowed to blast,
it is impossible to use the traditional drilling and blasting method.
Therefore, the solution is needed in this case.
Solution
General sequence for the normal
construction of shafts is: top-down tunneling. When the wellbore reaches a
certain height, the wall is built up down-top, and the tunneling and wall-laying
alternate. The process sequence of each section is drilling and blasting
firstly, then load out the gangue and rock, and finally builds the wall. Due to
the limitations of the community environment, it is not possible to use the
blasting tunneling, so it is recommended to use the raise boring machine
process for vertical shaft development.
Construction Process
The raise boring machine construction process includes pilot hole drilling and reaming drilling. That is, first drill into the positive guide hole, and then reverses count
The principle of the raise boring machine
process is to drive the hydraulic motor via the motor of the drilling machine.
The hydraulic motor drives the power unit and torque is transmitted to the
drilling tool system via hydraulic power, which drives the drill pipe and the
drill bit to rotate. The hob on the drill bit is under the action of the
drilling pressure, pure rolling and micro-slip along the working face of the
rock at the bottom of the well. At the same time, the axial pull and pressure
generated by the main cylinder also pass through the power head, and the drill
pipe acts on the drill bit, so that the hob of the drill bit rolls under the
action of the drilling pressure, generating an impact load, causing the hob
teeth to impact and squeeze the rock. Pressing and shearing, breaking the rock.
For the pilot hole drilling, the broken
rock cuttings are flushed by the circulating washing fluid when the guiding
hole is drilled, and the cuttings are lifted from the washing fluid to the
outside of the borehole along the annular space between the drill pipe and the
hole wall (see in Figure 2).
Figure 2 Raise Boring Machine Positively Hole Guiding
Process
"1-power head 2-drill rod 3-channel drill bit 4-mud from mud pump 5-loaded slag mud returned from annular space 6-mud circulation tank 7-mud pump"
For raise boring machine drilling and
tunneling, the rock debris fall directly into the lower roadway by their own
weight, and then cleaned out by the mucking machine or other means (as shown in
Figure 3).
Figure 3 Raise Boring Machine Negatively Hole Reaming
Process
In this example, ZFY2.5/400 (LM-400)
anti-drilling rig is used to drill, first drill 270mm guide hole until the
guide hole drills through the lower roadway, then remove the guide hole drill
bit, and connect the 2m diameter reaming drill bit. Then, expand the hole
down-up.
Figure 4 Raise Boring Machine
Figure 5 Reamer Bit
Figure 6 Hole Guiding Bit
Comparison Between Raise Boring Machine Technology and Traditional Blasting Construction Method
1. Fast Speed
In the traditional construction method, it
is necessary for the staff to carry out eye-catching, firing, slag, support and
other operations in each section of the wellbore. Compared with the traditional
construction method, the raise-boring machine technology has the following
advantages, which can significantly improve the construction progress:
1.1 Eliminate the process of drilling and
blasting
1.2 The gangue discharging is handled by
the transportation system of the lower roadway, especially when the shaft is
deeper, the higher efficiency of raise boring machine
1.3 As the personnel do not need to enter
the shaft during the construction process, and the lithology which the shaft
enters through is tight sandstone and limestone, it is not necessary to support
the wall in time to prevent injury
For example, in the North Second district
of Gujiao Malan mine, design diameter is 3m, full height is 112m, with the
application of raise boring machine technology, hole guiding time is 56.75h,
hole expanding time is 61.5h, 118.26h in total. While compared with similar
Zhenchengdi Mine, for 76m main coal bin, the construction operation time period
is more than 2 months by using traditional drilling and blasting method
2. High Efficiency
Traditional construction methods of per
shift includes drilling hole, blasting, supporting and gangue discharging,
which involves exhausting physical labor and difficult working conditions. In
the example above of Zhenchengdi Mine, more than 12 people per shift, and
advancing speed is 2m per shift. While using raise boring machine, only 4-5
people per shift, advancing rate is 1m per hour. The labor intensity and
construction conditions have been fundamentally improved.
3. Ensure Safety
Because construction workers don’t enter
the shaft, their safety is assured. The deflection rate is less than 1%, and
greatly reduces damage for surrounding rocks, thus guarantee the safety.
4. Low Cost
Reverse drilling can save a lot of material
cost, and personnel costs are lower than traditional construction methods.
Model Selection of Raise Boring Machine in
This Case:
1. Choose hole drilling and expansion
2. Choose raise boring machine parameter
Although this project only drills 100m,
considering actual application and other practical conditions, ZFY2.5/400
(LM-400) raise boring machine is chosen.
Technical parameters of ZFY2.5/400(LM-400)
are as below:
Technical verification is as below:
Due to the maximum downwards thrust of the
equipment is 2450KN, which is much larger than the thrust required for the
drilling guide hole. To meet the engineering requirement, the expansion tension
is verified below:
Actual working tension = Power head weight
+ hole drill bit weight + drill rod weight + maximum drilling pressure
Among which: power head and cylinder weight
40KN
Hole drill bit weight 25KN
Drill rod weight =155KG/m*400m*9.8N/KG=607.6KN
Maximum
drilling pressure can refer to the following table, if speed is 1500mm/h,
compressive strength is 80MPa, drilling pressure =477.5kN Then the actual work
pulls =40+25+607.6+477.5=1150.1KN
Table 1 (D=2.0m) Relationship between drilling speed
and drilling pressure
It
is generally required that the actual working force should not exceed 60% of
the maximum lift capacity of the rig. The maximum tensile force for hole
expansion of ZFY2.5/400 (LM-400) in this example is 3000KN, and the actual
working tensile force/maximum tensile ratio is 38%, which can meet the
requirement.
Contact us for more information:
Serena
E-mail: serena.fu@hot-mining.com
Whatsapp: +86 15108333341
Skype: serena20140924
Kyle
Email: kyle.lee@hot-mining.com
Whatsapp:+86 15756875803
Skype: +86 15756875803